Foster Clean Power
9.4 MWdc solar · 2.5 MW / 10 MWh storage
Led development and interconnection for a two-site portfolio near Arcata — 4.45 MWdc and 4.95 MWdc — under a power-purchase agreement with a Humboldt County community choice aggregator. It is the largest new community solar and storage project on the North Coast, sized to serve 3,000+ homes.
Outcome. A mis-recorded water easement and a PG&E easement sat on the planned access road. Fresh surveys and a revised layout, worked out with the local water district, cut the road cost from over $240,000 to about $60,000 and saved six weeks, without giving up the energy yield.